An Andersen EV charger for a period cottage in Ayot Green.
The old garage board couldn’t take a charger, so we found a better route: a new EV board at the intake and a discreet armoured cable run to an Andersen A2.

The new owner of a period cottage, who had taken the keys the evening before, wanted an Andersen A2 charger installed. The garage board was obsolete and over-committed, so a better supply point and route were needed.
At a glance
| Location | Ayot Green, near Welwyn (AL6) |
|---|---|
| Completed | September 2024 |
| Work | Home EV charger |
| Property | Period brick cottage |
| Time on site | Two days (11-12 Sep 2024) |
| SEG team | Jamie, Daniel and Luke |





What we found
- Garage board and both house boards were old-generation Square D - obsolete, with no DP RCBO or SPD available
- Garage board fed from the house on a 45A MCB with many unknown circuits - not suitable for a 32A charger
- Multiple C2 and C3 observations noted at the intake
- Brittle 100A Henley block; TN-S supply
- Water leak from a boss joint found dripping onto a board - dried and sealed as a temporary fix with client approval
- A redundant dead relay, doorbell transformer and unneeded socket in the intake cupboard
What we did
- Recommended and agreed a new charger position by the house intake instead of the garage
- Cleared space at the intake by relocating adaptable boxes and removing redundant equipment
- Replaced the brittle Henley block and installed a new 4-way FuseBox board with surge protection and a DP RCBO for the charger
- Ran EV Ultra SWA cable clipped at 400mm centres, discreetly behind planting, to the charger
- Installed the Andersen A2 7kW charger, using a modified gland arrangement to keep the IP seal
- Torqued all terminations to the manufacturer's figures and fitted IP cover plates and cable retainer
- Covered exposed single insulation in trunking
- Set up the CT clamp and load balancing, and resolved account set-up with Andersen's helpline
- Tested the new circuit: Ze, PFC, R1+R2, RCBO trip times and insulation resistance at 500V
Equipment used
- Andersen A2 7kW 32A charger
- FuseBox F2004M 4-way consumer unit with SPD
- DP RCBO
- EV Ultra SWA cable
- 100A Henley block
Need something similar in Ayot Green? See EV charger installation, or electricians near Ayot Green. Call 01727 238 999 or tell us about the job.
More recent local jobs
- Lighting, power, data, fire alarm and door entry for serviced apartments at 37 Doughty Street, Bloomsbury, London, 2022
- Cisco Wi-Fi, Verkada access control and AV for James Hambro's new Edinburgh office, Edinburgh, October 2026 (in progress)
- LD1 Aico smoke alarms for a sheltered housing scheme in Walthamstow, Walthamstow, October 2026 (in progress)
- Garden uplights and floodlights traced and fixed over two visits, Totteridge, September 2026
From SEG’s job records and engineers’ photos. Customer details are kept private.
Need it done by a date?
Tell us the deadline. We’ll tell you honestly whether we can hit it — and we usually can.