A Zappi EV charger and a new EV board in St Albans.
The supply and gas bonding needed upgrading before a family home could charge an electric car. We sorted both, then fitted and commissioned the charger.

The homeowners were switching to a fully electric car and wanted a myenergi Zappi on the side of the garage. The survey found the supply and bonding needed upgrading first, and the route had to avoid the underfloor heating.
At a glance
| Location | St Albans (AL4) |
|---|---|
| Completed | January 2026 |
| Work | Home EV charger and consumer unit |
| Property | Family home |
| Time on site | Survey (15 Sep 2025), install day (6 Oct 2025), connection and commissioning visit after the supply upgrade (26 Jan 2026) |
| SEG team | Jamie, Charlie, Chris and Josh |





What we found
- Main fuse labelled 60A with 16mm supplier tails - upgrade recommended for full EV use
- Gas bonding only 6mm - needed upgrading to 10mm
- Existing board (2021 works) had poor terminations to SWA and single insulation outside the enclosure
- Underfloor heating zones throughout the ground floor ruled out a route under the floor, so cables went above the skirting and through the garage
What we did
- Installed a new FuseBox EV board under the stairs with Type 2 surge protection (SPD), 100A main switch, a 32A 30mA RCBO for the charger and a 6A RCBO for future porch lighting
- Fitted a Henley block and ran tails to the new board
- Ran 6mm twin and earth plus a data cable for the charger in MT4 trunking through the garage
- Installed a black tethered myenergi Zappi on the side of the garage with a CT clamp, connected it to Wi-Fi and set it up
- Fitted and labelled a 32A rotary isolator next to the charger
- Upgraded the gas bonding to 10mm and labelled it
- Ran a lighting supply into the garage ready for the planned porch refurbishment
- Board left un-energised until Octopus Energy upgraded the incoming supply, then returned to connect, test and commission
Equipment used
- myenergi Zappi (black, tethered)
- FuseBox consumer unit with SPD1MT2 surge protection
- FuseBox 32A RCBO
- 32A rotary isolator
- MT4 trunking
- CT clamp
Need something similar in St Albans? See EV charger installation and fuse board replacement, or electricians in St Albans. Call 01727 238 999 or tell us about the job.
More recent local jobs
- 85-inch screens wall-mounted and a new network switch for Master Mix, Frogmore, November 2026
- Lighting, power, data, fire alarm and door entry for serviced apartments at 37 Doughty Street, Bloomsbury, London, 2022
- Cisco Wi-Fi, Verkada access control and AV for James Hambro's new Edinburgh office, Edinburgh, October 2026 (in progress)
- LD1 Aico smoke alarms for a sheltered housing scheme in Walthamstow, Walthamstow, October 2026 (in progress)
From SEG’s job records and engineers’ photos. Customer details are kept private.
Need it done by a date?
Tell us the deadline. We’ll tell you honestly whether we can hit it — and we usually can.