SHDF ventilation and fuse board upgrades in 440 Stevenage homes.

For Wates, under the Social Housing Decarbonisation Fund Waves 1 and 2: more than 830 new extractor fans, 53 new consumer units and 235 RCD upgrades, with a report for every home.

Dual-RCD consumer unit with its cover off, wired and ready for testing, in a Stevenage home

At a glance

SHDF Wave 1SHDF Wave 2
WhenApril to November 2023October 2023 to April 2025
Homes197243, plus 12 blocks and communal areas
Extractor fans360 dMEV fans (186 kitchen and WC, 174 bathroom)469 Envirovent Infinity fans (244 kitchen and WC, 225 bathroom), plus 8 Greenwood fans
Electrical upgradesNew fused spurs where needed53 new consumer units, and 235 RCDs changed to Type A in 138 homes
Core holes and window kits96 core holes, 26 window fan kits143 core holes, 120 window fan kits

Both waves were for Wates, as main contractor, in social homes across Stevenage: more than 830 extractor fans in 440 homes in two years.

Why the ventilation came first

SHDF pays for social homes to be insulated and made more energy efficient. A warmer, more airtight home also traps moisture, so the programme put better extraction into kitchens, bathrooms and WCs alongside the fabric work. We fitted Envirovent Infinity extract fans throughout, replacing old or missing fans.

Wave 1: 360 fans in 197 homes

From April to November 2023 we fitted 360 decentralised mechanical extract ventilation (dMEV) fans: 186 in kitchens and WCs and 174 in bathrooms, where the bathroom fans ran at safety extra-low voltage. That meant 96 new core holes, 26 window fan kits, fused spurs where needed, and existing fans overhauled where they were sound.

Wave 2: the fans

  • 469 Envirovent Infinity fans: 244 in kitchens and WCs and 225 in bathrooms, including a handful in communal areas.
  • 143 new core holes through external walls, with external grilles fitted from access equipment where needed, and 120 window fan kits in 88 homes where a wall fan wasn’t possible.
  • Existing fans overhauled where they were sound (20), moved (10) or put on a new fused spur (10), rather than replaced by default.
  • 8 Greenwood fans in four homes where a different model suited the room.
New Envirovent Infinity extract fan on a tiled bathroom wall
Bathroom: new Infinity fan
Extract fan fitted in a window pane with a window fan kit
Window fan kit, where a wall fan wasn’t possible
New extract fan high on a WC wall with its pull cord
WC: new fan
Core drill cutting a hole through a tiled bathroom wall
Core drilling through the wall
New external vent grille on a brick wall above a window
Outside: the new external grille
Infinity fan mounted with its cover off, during installation
During: fan mounted, before the cover goes on

Wave 2: the fuse boards and RCDs

A new fan is only as safe as the circuit feeding it, so every home had its consumer unit and earthing checked before the fan went in.

  • 235 RCDs changed to Type A in 138 homes. The fans’ instructions call for Type A protection, and many homes still had older Type AC devices.
  • 53 new consumer units: dual-RCD, metal-clad boards with built-in Type 2 surge protection. The rule agreed with the landlord: replace the board if it isn’t a recognised make, has no spare way for future solar panels, or has visible defects. See consumer unit replacement.
  • Main bonding checked and recorded, with a Minor Works Certificate for the new circuit work.
New metal-clad dual-RCD consumer unit fitted in a home
A new dual-RCD consumer unit
Consumer unit with its cover off, neatly wired, during testing
Inside a new board, before the cover goes on
Consumer unit with Type A RCDs fitted and labelled
Type A RCDs fitted and labelled

A completion report for every home

Our engineers completed a photo report on a tablet in every home before signing it off, overseen by our senior contracts manager. Each one records:

  • the earthing arrangement and the consumer unit, with the RCD type;
  • before, during and after photos of every fan, the core hole and the external grille;
  • the fused spur and its 3A fuse, and the fan’s quality-control number;
  • main bonding, the certificate issued, and anything else the engineer found.

The main contractor and landlord can check any home from its report, without another visit.

Monitoring and other work

Early in the programme we also fitted Aico HomeLINK gateways and 48 Ei1025 environmental sensors in 12 homes, which monitor temperature and humidity so the landlord can spot damp and mould risk early. Alongside the SHDF work we ran site set-up power for the compounds and hoists, tested the site cabins, and handled responsive call-outs for Wates in the same streets. See site set-up and temporary power and our work in Stevenage.

Planning retrofit or ventilation works? We work for main contractors and housing providers on SHDF, Warm Homes and planned programmes. See housing providers and our SHDF works for Novus, or call 01727 238 999.

Questions

Why does a retrofit need new extractor fans?

Insulation and new windows make a home more airtight. Without enough extraction, moisture from cooking and bathing stays inside, and condensation and mould follow. SHDF retrofit work follows PAS 2035, which looks at ventilation whenever a home’s fabric is upgraded.

Why did you change so many RCDs?

The fans’ installation instructions call for a Type A RCD. Many of the homes had older Type AC RCDs, so we changed them to Type A rather than leave the new fans on protection the manufacturer doesn’t allow for.

When does a fuse board need replacing on a job like this?

On this contract the rule agreed with the landlord was simple: replace the consumer unit if it is not a recognised make, has no spare way for future solar panels, or shows visible defects. Otherwise keep it and change any RCD that isn’t Type A. See does my fuse board need replacing?

Can you work in occupied homes?

Yes. We book visits around residents, keep dust and disruption down, and record and rebook any no-access visits.

Written by SEGplc from our contract records and completion reports. Figures count each item once per home. Last updated 26 October 2026.

Need it done by a date?

Tell us the deadline. We’ll tell you honestly whether we can hit it — and we usually can.

Contact

Talk to SEG

Questions about a job, a certificate or a programme of works? Call the office or send a message. Head office in St Albans, serving Herts, Beds, Bucks and London.

Emailhello@segplc.comPhone01727 238 999Also on0345 3 822 833OfficeSEG House, 192 Watford Road, Chiswell Green, St Albans, Herts AL2 3EBHours7 days, 7am–10pm · emergencies by arrangementLeadershipMichael Simm · Russell Solts
Call nowGet a quote