Fibre link between two buildings, Welwyn Garden City.

A new OM4 fibre link joining a business's existing building to the one next door, installed in a day.

New comms room cabinet and trunking installed by SEG in Welwyn Garden City

A Welwyn Garden City business had taken over the building next door and needed the two networks joined. We ran a new OM4 fibre link between the comms cabinet in their existing building and a new cabinet in the one they had just acquired. We were on site for a single working day.

The brief

The business had acquired the adjacent building and needed the two networks joined. A copper cable between buildings can hit distance and interference limits, and fibre avoids both, so the request was for a fibre link run internally, from the ground-floor comms cabinet in the existing building to a first-floor cabinet in the new one. We surveyed in September and quoted from the survey.

What we installed

  • One OM4 multimode fibre cable between the two buildings, run internally the whole way.
  • Two fibre termination trays, one in each comms cabinet, with the fibre terminated to LC connectors at both ends.
  • One 1 m OM4 LC to LC patch lead at each end, so the link plugs straight into the network equipment.
  • Trunking and fixings for the route, with the fibre clipped in and the trunking labelled so anyone opening it later knows it carries fibre.
  • Fire-sealed wall entries where the cable passes between rooms, so the new route does not weaken the fire separation.
  • Testing and certification of the link to OM4 standards, which was part of the quoted scope.

The day

Our engineer arrived at 9:30 on Friday 9 October. The new comms room came first: the wall entry was fire-sealed, the trunking was fitted, the fibre clipped in, the termination tray fitted and the ports labelled and working by early afternoon. Then the old comms room: the same sequence, ending with the fibre panel in and working. Anything we had moved to get the cable through was put back, and the van was packed away and off site by 3:30 in the afternoon.

The work, in photos

New comms room cabinet on the wall before the trunking and fibre were installed
New comms room, before the trunking went in
New comms room cabinet with trunking dropping to the floor, work finished
New comms room, finished
Open fibre termination tray with coiled fibre tails and LC adaptors fitted in the new comms room
Fibre termination tray, new room
Close-up of the LC fibre adaptors with coloured fibre tails on the tray
LC connectors on the tray
Cable entering white trunking through a wall opening sealed with fire-stopping mastic
Where the cable passes through the wall, fire-sealed
Trunking fixed to a brick wall above containment with the fibre clipped in, old comms room
Old comms room: trunking up, fibre clipped in

Photos taken on site, 9 October 2026.

What was not in our scope

The quote covered the fibre link, its containment and its testing. Patch panels, switches and other active equipment were not part of it, and neither was making good beyond a standard finish. Keeping the job to the cabling is common when the customer has an IT provider who looks after the network itself. If you want us to supply and set up the switches too, say so at survey and we will price it.

Linking buildings, floors and units

The same approach works for offices that expand next door, warehouses with a separate office block, and schools or care homes with outbuildings. See our data cabling page, or the work we did for a hotel network upgrade.

Joining two buildings or floors? Call 01727 238 999 or tell us about the site. We survey the route first, then quote a fixed price for the cabling and testing.

Questions we’re asked

Why use fibre between two buildings?

Fibre carries data over longer distances than copper without signal loss, and it is not affected by electrical interference. It also keeps the two buildings electrically separate, which avoids problems between different power supplies and earthing.

What is OM4 multimode fibre?

OM4 is a grade of multimode fibre made for short to medium links inside and between buildings. It supports 10 Gb/s over distances of about 400 metres, which is far more than most office links need, and it leaves room for faster equipment later.

Can fibre be run between buildings without digging?

Sometimes. Where there is a clear internal route, as there was here, it can run in trunking through the buildings. Where there is not, it needs external ducting or armoured cable. That is decided at the survey.

How long does a link like this take?

A single link between two cabinets can often be done in a day, as it was here. The time depends on the route length, the wall entries and how easy the cabinets are to reach.

Do you supply the switches as well?

We can. On this job the customer's IT provider looked after the active equipment, so the quote covered the fibre, containment and testing only.

Do you work in Welwyn Garden City?

Yes. This job was in Welwyn Garden City, and we also cover Hatfield, Hertford, St Albans and the rest of Hertfordshire, Bedfordshire, Buckinghamshire and London.

Written by SEGplc. Last updated 2 November 2026.

Need it done by a date?

Tell us the deadline. We’ll tell you honestly whether we can hit it — and we usually can.

Contact

Talk to SEG

Questions about a job, a certificate or a programme of works? Call the office or send a message. Head office in St Albans, serving Herts, Beds, Bucks and London.

Emailhello@segplc.comPhone01727 238 999Also on0345 3 822 833OfficeSEG House, 192 Watford Road, Chiswell Green, St Albans, Herts AL2 3EBHours7 days, 7am–10pm · call-outs every dayLeadershipMichael Simm · Russell Solts
Call nowGet a quote